This week’s updates from the Wisconsin Department of Transportation (WisDOT) on road construction projects for Barron, Burnett, Polk, Rusk, Sawyer, and Washburn counties.
Barron County
- No current projects.
Burnett County
- No current projects.
Polk County
Highway: US 63
- Location: St. Croix/Polk County line to County J south of the village of Clayton
- Schedule: April 12 to late September
- Cost: $5.71 million
- Description: Replacing the pedestrian underpass east of 7th Street in the village of Clear Lake; milling off 2 inches of asphalt pavement and placing 3.25 inches of new asphalt; adding shoulder gravel to accommodate the highway profile increase; realigning the approach of County A/F at US 63 to achieve better sight distance at the intersection; realigning the approach of 60th Avenue at US 63; expanding the intersection tapers to meet current design standards; replacing guardrail; and cleaning, lining or repairing culverts and installing new end walls on some structures.
- Traffic impacts: US 63 is reduced to a single lane of traffic at the pedestrian underpass east of 7th Street in Clear Creek.
- Traffic is controlled by temporary signals, and 7th Street South is closed.
- The 60th Avenue east and west intersections at US 63 are closed today through the end of next week.
- Lane closures controlled by flagging are being used as necessary for culvert work.
Rusk County
- No current projects.
Sawyer County
- No current projects.
Washburn County
Highway: WIS 77
- Location: County I west of the village of Minong east to County M
- Schedule: April 10 to late July
- Cost: $8.48 million
- Description: Removing a portion of the existing pavement and placing new asphalt pavement; cleaning, repairing or installing new culverts; reconstructing sidewalk curb ramps in the village of Minong; replacing deteriorated curb and gutter in the village of Minong; replacing guardrail; placing centerline rumble strips in rural areas; and installing new pavement markings.
- Traffic impacts: Motorists on westbound WIS 77 will encounter a shoulder closures in the village of Minong for curb and gutter work.
Related:
- Washburn County Highway Commissioner Issues Multiple Road Work Notifications
- Finishing Work On US 53/63 Interchange Project In Trego Set To Begin
Highway: US 53
- Location: Pine Grove Road southeast of Shell Lake to Wildcat Road southeast of Spooner
- Schedule: Aug. 15, 2022, to October 2023
- Cost: $16.8 million
- Description: Removing the existing pavement and a portion of the existing base course; placing a new base aggregate layer for drainage and new concrete pavement; replacing storm sewer, culverts, curb and gutter; reconstructing the approaches to US 53 from existing intersections; replacing shoulder rumble strips; and placing pavement markings.
- Traffic impacts: One lane of traffic in each direction is being maintained on the southbound lanes.
Last Update: Apr 28, 2023 2:19 pm CDT