Northwest WI Regional Weekly Construction Update - Dec. 2, 2022

Road construction project updates for Barron, Burnett, Polk, Rusk, Sawyer, and Washburn counties.

Northwest WI Regional Weekly Construction Update - Dec. 2, 2022

This week’s updates from the Wisconsin Department of Transportation (WisDOT) on road construction projects for Barron, Burnett, Polk, Rusk, Sawyer, and Washburn counties.

Barron County

  • No current projects.

Burnett County

  • No current projects.

Polk County

  • No current projects.

Rusk County

  • No current projects.

Sawyer County

  • No current projects.

Washburn County

Highway: US 53

  • Location: Between Mackey and Ross roads in the town of Trego
  • Schedule: March 17, 2021, to November 2022
  • Cost: $17.65 million
  • Description: Reconstructing US 53 from Mackey Road to existing US 63, relocating US 63 to closely follow the existing Wild Rivers State Trail and constructing a new grade separated interchange connecting US 53 with realigned US 63, new west frontage road from Mackey Road to County E and turn lanes along US 53 at existing intersections, including Mackey, O’Brien and Ross roads.
  • Traffic impacts:
    • None; project complete for 2022. Restoration work is planned to occur in the spring.

Editor's note: this will be our final weekly construction update for the year as all projects have been completed. We will resume these weekly posts in the spring when construction projects resume.

Read more news & info on DrydenWire.com

Last Update: Dec 02, 2022 9:11 am CST

Posted In

Outdoors

Share This Article

Loading...
Loading...
Loading...